PeopleTools 8.55 is a prerequisite of PS CS 9.2, and will provide facelifts to the user interface, such as a more contemporary look to different menus and functions. Released in December 2015, PS CS 9.2 delivers new visual guides to help casual users better navigate the system and execute activities more easily. ASR has begun the initial stages of planning for this project. Carrie Otto has agreed to lead the PS CS 9.2 upgrade project.
A rough timeline has been developed by the Administrative Computing Steering Committee (ACSC) and the Operation Advisory Steering Committee (OASC). Visit The Record blog to see the timeline »
May-June 2016
- Preparation activities: gather, itemize, and familiarization of resources
- Build project plan details
- Form teams, organize project
July-January 2017
- July-August
- Educate IT staff and gain familiarity of PS9/T8.55
- Review release notes
- Release test instance, OIT
- September-January
- ASR fit gap kick-off, October
- Fit gap & priority determinations
- Review/redesign business process
- MIDHEUG updates from other schools upgrading
January-April 2017
- Testing of tools
- Update documentation for tools
- Determine tech resources for code, design, and testing
May 2017-February 2018
- Finalize CS 9.2 design changes
- Retrofits and coding, developers
- Testing
- Training, communication, documentation, and change control
February 2018
- Go live